ROC_Out not getting triggered and ASSERTION failed issue

$
0
0


Hi Experts,

 

I am facing an issue wherein in WEB UI PO confirmation is done and instead of ROC_Out ..RON_out is getting triggered.

In addtion to that i am getting an issue of ASSETION failed..but XML RON_out is getting generated and it is successful

ASSERTION_FAILED

/SCA/TSODM====================CP

|>>>>>|  ASSERT lt_return IS INITIAL.

 

I have activated ODM as per SAP note and made sure that ODM is maintained correctly.

 

In addition to that i have tried to activate planning object structures through /SCA/TSDM09 but getting the messaged that 9AINV1......planning structure object activation failed.

 

Could you please let me know the possible causes.

 

Also for ROC_Out Issue which is not triggering

 

I tried maintaining below validation setting :

 

Profile:POC3

Validation check:PO_PUBLISH_ACCEPTED_ITEMS

Validation check:PO_PUBLISH_CHANGED_ITEMS

Validation check:PO_PUBLISH_ACCEPTED_ITEMS

 

Status i have maintained as Inactive.

 

Please let me know what could be the solution so that ROC_Out will get triggered and also i would be able to resolve assertion issue and should be able to activate planning structure object.

 

I think all the above are related to single issue thats the reason i am posting this in one thread.

 

Regards

shailesh