Hi All,
I have a behavior in our Client Production System.
We have setup a process in which if a PO confirmation Dates are -5 / + 5 days appart then that line item should result in Manual Approval Required.
Even though a PO line item is in Status "Manual Approval Required" a XML message is triggered and a AB confirmation gets created in ECC.
Issue we faced:- even if the Confirmation Dates are within range still the PO was ending up in Manual Approval specially if vendor enters multiple Schedule lines for the same PO line item with Dates with in +/- 5 days.
In our Test system , we implemented notes given by SAP to fix the above issue the issue looks fixed but,
Now the behavior is if the line item is having Status "Manual Approval Required", NO XML messages are getting triggered for a PO with Confirmation date beyond +/- 5 days. Once the the approval is given and Schedule line is Adopted the XML is getting triggered correctly.
I want to know from all the Experts on to understand which behavior is correct is Production correct(excluding the Bug) or the Test systems not triggering XML unless the Manual Approval is given.
I did read SAP help but i am not understanding since SAP mentions both behavior not Clear when such behavior should occur.
Please help to understand thsi behavior.
Please advise.
Thx
MJ